PHOTO GALLERY CONSTRUCTION

Cold room

Mork Calismalari

Preparing the cold room

Sanitary facilities

On Tesla
Installation of sanitary facilities

Electrical Installation

Concrete icindeki borulara kablolar cekildi

Pipes have been prepared in the concrete and now the cables are being pulled in

Window

Peceriler takildi icerde calismalar basliyabilir.
The windows are in now installation work can begin

CEM House

planned completion autumn 2021

Loan Signing at the Bank

We applied to seven banks and after a lot of time, patience and professional work, we signed at VR Bank Neu-Ulm.
We thank Cevat Seven, Hıdır Cıhan and Merdal Yalçın for their sacrifices.
Wir haben sieben Banken angefragt, es hat sehr viel Zeit und Nerven gebraucht bis wir von der VR Bank Neu-Ulm eine Zusage bekommen haben.
Unseren Dank an Cevat Seven'in, Hıdır Cıhan und Merdal Yalçın für die Bürgschaften bei der Bank.

Evacuating the Association

The building had to be completely gutted before demolishing it.

Vor dem Abriss musste alles ausgeräumt werden..

Evacuating the Association

20 years later, you will be able to see what is happening, and you will have a lot of energy and energy.

A lot of things accumulated over the course of 20 years. Clearing them out and disposing of them was time-consuming and expensive.

Back yard

Dernegin güzel bihcesi vardi, maalesef kimse kullanamıyordu bakımsızdı.
Hasan abi Ceviz ağacını kendin diktin ve kendin kestin.

We had a beautiful garden, but unfortunately it was not accessible. Hasan had planted a walnut tree, and now he was allowed to cut it down himself.

Old building

This is a good idea, it's easy to see what's going on.
Senin içinde büyüdük, teşekkürler.
The old clubhouse was beautiful and we have many fond memories of it, but ultimately it was dilapidated, old and did not meet our needs.

Empty land after building demolished

Dernegin arsasisi 1000 m²
The property covers approx. 1000 m²

Sheet pile walls

Groundworks were 'Spundwände' to a depth of 10m to prevent landslides and prevent water during construction time.
Erdarbeiten, damit die Erde beim Ausheben nicht hereinrutscht und zur Grundwasservorbeugung haben wir 10m tiefe Spundwände hereingerammt.

Micropiles

Binayı taşıması için toprak zemine 60 tane Beton Direk
atildi.
In order to ensure that the building stands later, 60 micropiles were driven 10m deep into the ground.

Micropiles

This is what you want from the director.
Although very expensive and time-consuming, the entire structure is supported by these arrows. They form its foundation.

soil studies

There was no calculation, the land was measured by a private company. A treatment plan was made according to the foreign waste and substances inside and they were transported to special places and disposed of.
Erdarbeiten, mit said wir nicht gerechnet hatten: Das ausgegrabene Material wurde von einer Umwelttechnik Firma auf Schadstoffe untersucht und fachgerecht entsorgt.

Sheet pile walls

Çok zaman aldı, toprağı kazınca kaymaması için 'cross carrier' takıldı.
To prevent the sheet pile walls from being dented during the excavation work, cross beams were installed.

Crane

Finally: The crane is in place and construction can begin.

Excavation work basement

It was not easy to dig out earth through the crossbeam. A mini excavator was used, which was also very time-consuming.

Groundwater

If the sheet pile turn didn't exist, we would have a huge problem with groundwater.
In the old building, groundwater was pumped out day and night; that will not happen for the new clubhouse.




Preparing the elevator shaft

Micropiles

The micropiles will later be concreted into the subsoil.
Here they are cut to size and fixed into the concrete with steel plates.

Basement work

Since we had a groundwater problem, the basement was built to be waterproof.
A special company was commissioned to do the sealing.
Since we build energy efficiently, we naturally have full insulation in the basement.

Basement work

Basement insulation







Basement work

A lot of steel was used.
The amount of steel was calculated by the structural engineer and
The structural engineer was then checked by a structural engineer.
It all cost a lot of money, but nothing comes from nothing!

Columns for the Great Hall

Since we need access to the rear parking spaces, the ground floor is smaller than the upper floor.
Some pillars were necessary for this.

The rear part of the building



The walls are finally standing!
The building is taking shape..

Main entrance ground floor


The walls are finally standing!
The building is growing...




Great Hall

Here, 12 windows are created in the Great Hall in reference to the 12 Imams.






Great Hall

The large hall is an impressive 220m².




First floor

Ground floor and first floor are standing.

Second story


Since we build with precast concrete parts, the shell was completed relatively quickly
With precast concrete parts, preparatory work is essential,
we had to take everything into account in advance.
The plant planner plays an enormously important role here.
Let’s hope everything has been thought of!
























Ceiling of the second floor

Here we see the light shafts of the 2nd floor corridor









Roof

The flat roof is still being built here.
The installation of a photovoltaic system is also planned.